European Data Centres MarketView Q4 2021

February 18, 2022

Looking for a PDF of this content?

Key points include:

- Data centre take-up (380MW) nearly doubled in 2021 due to strong demand from hyperscalers.

- Nearly 400MW of new supply came online in 2021 despite construction delays that stemmed from labour shortages and supply chain issues.

- Another 356MW of supply is expected to come online across FLAP markets despite continued challenging conditions.